Canadian Construction Site Terminology Complete Guide — Expressions Different from Korea

If you’re new to Canadian construction sites, you’ll encounter unfamiliar terminology even if your English is fairly solid. Some terms are conceptually similar to what you’d use in Korea but…

If you’re new to Canadian construction sites, you’ll encounter unfamiliar terminology even if your English is fairly solid. Some terms are conceptually similar to what you’d use in Korea but expressed differently; others don’t exist in the Korean context at all; and conversely, Canada has its own systems and regulations you’ve never seen before. This guide is a practical reference covering key terms actually used on Canadian construction sites, organized by category.

1. Project Structure & Contracts

Canadian construction projects are clearly divided by roles and responsibilities through contracts. Knowing the terminology precisely is essential to understanding your position and scope of responsibility.

TermKorean EquivalentDescription
Owner발주처, 건축주The party that commissions the project
General Contractor (GC)종합건설사, 원도급사The prime contractor overseeing the entire project
Subcontractor (Sub)하도급사A trade contractor hired by the GC for a specific scope (electrical, plumbing, steel, etc.)
Prime Contractor원수급자Under WorkSafeBC, the party with overall site safety responsibility. Often the same as GC but a legally distinct concept
Consultant / Design Team설계사, 감리단The Architect, Structural Engineer (SE), MEP Engineers responsible for design and field review
Architect of Record (AoR)설계 책임 건축사The licensed architect who signs the building permit and occupancy documents
Engineer of Record (EoR)설계 책임 엔지니어The P.Eng who signs off on each discipline (structural, mechanical, electrical)
Owner’s Representative감독관, CMThe person managing the project on behalf of the Owner
Trades전문 공종Collective term for all specialty trades: Electrical, Plumbing, Steel, Waterproofing, etc.
Lump Sum Contract총액 도급 계약Fixed total price contract
Unit Price Contract단가 계약Payment based on quantity × unit price
Cost Plus Contract실비 정산 계약Actual cost + fee
GMP (Guaranteed Maximum Price)최대 보증 금액 계약Cost Plus with a capped maximum
Tender / Bid입찰Tender is more common for public work; Bid for private projects
RFP (Request for Proposal)제안 요청서Procurement that evaluates methodology and technical approach, not just price
Change Order (CO)설계 변경, 추가 공사 지시서Formal document for work outside the original contract scope
PCO (Potential Change Order)변경 가능성 문서Preliminary review stage before a CO is finalized
RFI (Request for Information)질의서Formal query from the contractor to the design team on unclear design items
Submittal자재 승인 신청서Formal submission of materials/products to the design team for approval
Shop Drawing시공 상세 도면Prepared by fabricator or contractor; approved by design team before fabrication/installation
As-Built Drawing준공 도면Final drawings revised to reflect actual constructed conditions
Deficiency List / Punch List하자 목록List of incomplete or defective items identified before substantial completion
Substantial Completion실질적 준공The state when the building can be used for its intended purpose; triggers warranty and lien periods
Holdback유보금10% of contract value held back under provincial Lien Acts (BC: Builder’s Lien Act)
Lien유치권A legal claim registered against real property for unpaid construction work
Warranty Period하자 보증 기간Period after substantial completion during which the contractor is responsible for defects; varies by trade

2. Permits & Administration

The following is based on BC. Terminology is largely consistent across provinces, though specific procedures differ.

TermDescription
AHJ (Authority Having Jurisdiction)The authority with permitting power — in BC, typically the local municipality’s Building Department
Building PermitThe foundational permit required from the AHJ before construction begins
Mechanical PermitSeparate permit for mechanical systems (HVAC, exhaust, etc.)
Plumbing PermitSeparate permit for plumbing systems
Electrical PermitSeparate permit for electrical work (BC: administered by Technical Safety BC)
Development PermitLand use/planning permit required before the Building Permit
Occupancy Permit (OCP)Final permit required to occupy and use the building
BCBC (BC Building Code)BC’s adopted and amended version of the National Building Code
NBC (National Building Code of Canada)The national model code adopted by provinces
InspectionAHJ Building Inspector’s review after completion of each phase
Special InspectionThird-party inspection for specific scopes: high-strength concrete, structural welding, SFRM, etc.
Field ReviewDesign engineer’s or architect’s on-site verification that construction matches design intent
VarianceAn approval to waive or relax a code requirement for a specific project
Code ComplianceWhether the work meets code requirements
Non-ConformanceA condition where work does not meet code or contract requirements
Close-in InspectionInspection before drywall installation, after all in-wall rough-in work is complete

3. Design & Structure

TermKorean EquivalentDescription
P.Eng (Professional Engineer)기술사 (유사)A licensed engineer registered with the provincial engineering association (BC: EGBC); authorized to stamp drawings
EIT (Engineer-in-Training)수련 엔지니어Pre-P.Eng stage; eligible to write P.Eng exam after required experience
Geotechnical Report지반 조사 보고서Soil investigation report
IFC (Issued for Construction)시공용 도면The permitted drawing set used for construction
IFR (Issued for Review)검토용 도면Drawings distributed for review before approval
Structural Drawing (S-Series)구조 도면Numbered S1, S2…
Architectural Drawing (A-Series)건축 도면Numbered A1, A2…
Civil Drawing (C-Series)토목 도면Numbered C1, C2…
Grade Beam기초 보Horizontal foundation beam at grade level
Spread Footing독립 기초Isolated footing under a column
Mat Foundation매트 기초Full-coverage slab foundation
Slab-on-Grade (SOG)기초 슬래브Concrete slab poured directly on prepared subgrade
Composite Deck합성 데크Steel beam + metal deck + concrete composite floor system
HSS (Hollow Structural Section)각관, 원형관Square, rectangular, or round hollow steel sections; written as HSS 4x4x1/4
W-Shape / Wide FlangeH형강Written as W8x31, W12x50 (imperial units)
LVL (Laminated Veneer Lumber)집성재 보Engineered lumber beam used for long spans in wood-frame construction
Glulam (Glued Laminated Timber)집성목Used in large timber structures
CLT (Cross-Laminated Timber)직교집성판Used for walls and floors in mass timber structures; rapidly growing in Canada
Bearing Wall내력벽A wall that transfers vertical loads
Shear Wall전단벽A wall that resists lateral forces (wind and seismic)
Moment Frame모멘트 골조A frame where beam-column connections transfer moment
Braced Frame가새 골조A frame that resists lateral loads through bracing members
Drag Strut / Collector집력재A structural member that collects and transfers lateral loads to shear walls
Camber캠버A pre-induced upward curve in a steel beam to compensate for anticipated deflection under load
Deflection처짐Downward displacement of a structural member under load
Embedment매립, 앵커 매립Steel hardware embedded within concrete
Rebar / Reinforcement철근Bar sizes in imperial: #4 = 1/2 inch diameter, #5 = 5/8 inch diameter, etc.
PT (Post-Tensioning)포스트텐션Tensioning of steel tendons after concrete is placed
Topping Slab토핑 슬래브A thin concrete layer poured on top of existing slabs or decks

4. Architectural Finishes & Envelope

TermKorean EquivalentDescription
Building Envelope건물 외피All elements separating interior from exterior: walls, roof, windows
Rainscreen레인스크린An exterior wall system with an air gap behind the cladding to drain water; nearly mandatory in BC
Vapour Barrier방습층Membrane that limits moisture vapour transmission
Air Barrier기밀층A system that controls air infiltration; distinct from vapour barrier
Firestopping방화충전Sealing penetrations and joints in fire-rated assemblies
Fireproofing방화피복Fire-resistance protection applied to structural steel
EIFS (Exterior Insulation Finishing System)드라이비트Exterior insulation + mesh + finish coat system
Soffit처마 밑면The horizontal underside of a roof overhang or beam
Fascia파사드 마감판The vertical finish board at the edge of a roof
Parapet파라펫A low wall at the perimeter of a flat roof
Curtain Wall커튼월A non-structural glass and aluminum exterior wall system
Spandrel스팬드럴Opaque panel in a curtain wall system that conceals the floor slab edge
Fenestration창호Formal term for all windows, doors, and skylights in a building
IGU (Insulated Glass Unit)복층 유리Double- or triple-pane glass with sealed air/gas space between layers
Gyp Board / Drywall석고보드The most common interior wall finish; often shortened to “Gyp”
Type X Gypsum Board내화 석고보드5/8 inch fire-rated gypsum board used in fire-rated assemblies
Resilient Channel탄성 채널Sound-isolation channel installed between gypsum board and framing
T-Bar CeilingT바 천장Suspended grid ceiling system with lay-in tiles; standard in commercial interiors

5. MEP (Mechanical, Electrical, Plumbing)

TermDisciplineDescription
MEPAllMechanical, Electrical, and Plumbing — the three primary building systems disciplines
HVACMechanicalHeating, Ventilation, Air Conditioning — the entire climate control system
AHU (Air Handling Unit)MechanicalConditions air (heat/cool/filter) and distributes it to occupied spaces
RTU (Rooftop Unit)MechanicalA self-contained HVAC unit mounted on the roof
VAV (Variable Air Volume)MechanicalModulates airflow to each zone based on load
MAU (Makeup Air Unit)MechanicalA unit dedicated to supplying outside (fresh) air
HRV (Heat Recovery Ventilator)MechanicalEnergy recovery ventilation unit that transfers heat from exhaust to supply air
ERV (Energy Recovery Ventilator)MechanicalHRV with added moisture exchange capability
DamperMechanicalA movable blade in a duct that regulates airflow
Fire DamperMechanicalDamper installed at duct penetrations through fire-rated assemblies
Smoke DamperMechanicalDamper designed to prevent smoke migration
Combination Fire/Smoke DamperMechanicalRated for both fire and smoke control
DX (Direct Expansion)MechanicalRefrigerant-based cooling (standard air conditioning)
Chiller / BoilerMechanicalCentral equipment that generates chilled water / hot water
FCU (Fan Coil Unit)MechanicalA terminal unit with a coil and fan connected to chilled/hot water piping
Domestic WaterPlumbingPotable and service water supply
Sanitary / DrainPlumbingWastewater drainage system
Storm / RainwaterPlumbingStormwater drainage system
Grease TrapPlumbingInterceptor that captures grease before it enters the sanitary system
Backflow PreventerPlumbingDevice that stops water from flowing backward into the supply
CleanoutPlumbingAccess point for clearing drain blockages
HydronicPlumbing/MechanicalA heating or cooling system that uses water as the heat transfer medium
In-Floor RadiantMechanicalRadiant floor heating using hot water tubes; similar in principle to Korean ondol
Panel BoardElectricalDistribution panel (breaker panel)
Switchgear / SwitchboardElectricalMain service equipment for high-voltage power distribution
TransformerElectricalVoltage transformation equipment
EMT (Electrical Metallic Tubing)ElectricalThin-wall metal conduit; the most common type for interior use
ConduitElectricalGeneral term for any raceway that protects electrical wiring
Cable TrayElectricalOpen ladder or trough system that supports bundles of cables
Circuit BreakerElectricalOvercurrent protection device
GFCI (Ground Fault Circuit Interrupter)ElectricalRequired in wet locations such as bathrooms and kitchens
AFCI (Arc Fault Circuit Interrupter)ElectricalArc-fault protection required in bedrooms and other specified areas
Generator / GensetElectricalEmergency standby generator
UPS (Uninterruptible Power Supply)ElectricalBattery backup system for continuous power
Low Voltage (LV)ElectricalLow-voltage systems including data, security, communications, and fire alarm
Fire AlarmFire ProtectionFire detection and alarm system; administered by Technical Safety BC in BC
SprinklerFire ProtectionAutomatic sprinkler system designed to NFPA 13 standards

6. Civil & Foundation

TermDescription
ExcavationRemoval of earth to a required depth
Cut and FillBalancing earthwork by cutting high areas and filling low areas
BackfillReplacing soil around a foundation or structure after construction
CompactionMechanical densification of soil; typically 95%+ Proctor density required
ShoringTemporary support for excavation walls or existing structures
LaggingTimber planks or boards placed between soldier piles to retain soil
Tie-Back / Soil AnchorEarth anchor drilled into soil to support shoring walls
DewateringRemoval of groundwater during excavation
Frost Line / Frost DepthDepth to which soil freezes; approximately 0.3 to 0.6 m in BC Lower Mainland, deeper inland
Bearing CapacityThe maximum load a soil can support per unit area
SettlementDownward movement of a foundation due to soil compression
Pile / CaissonDeep foundation element; types include Driven Pile and Drilled Pier
Helical PileScrew-type pile installed by small equipment; widely used in BC
SubgradeThe native soil below a foundation or pavement structure
Sub-base / Base CourseGranular layer (gravel, crushed stone) beneath a slab or pavement
Granular FillCompacted gravel or crushed stone used for fill
GeotextilePermeable fabric used for filtration, separation, or reinforcement
SwaleA shallow, sloped channel designed to manage surface water runoff

7. Site Management & Safety

TermDescription
Prime ContractorThe party designated by WorkSafeBC as responsible for overall site safety
WorkSafeBCBC’s workplace safety authority — equivalent to Korea’s Ministry of Employment and Labor combined with KOSHA
OHSR (Occupational Health and Safety Regulation)WorkSafeBC’s core safety regulations
Site Safety PlanA documented plan outlining safety procedures for the project
FLHA (Field Level Hazard Assessment)A task-level hazard identification completed before each work activity
Toolbox TalkA brief pre-task safety meeting with the crew
MSDS / SDS (Safety Data Sheet)Hazardous material information sheet required for chemical handling
PPE (Personal Protective Equipment)Hard hat, safety boots, high-vis vest, gloves, eye protection, etc.
Fall Arrest SystemEquipment (harness, lanyard, anchor) that stops a worker in a fall
Hot Work PermitRequired authorization before any work involving open flame or sparks
Confined SpaceAny space with limited entry/egress; requires permit and attendant before entry
Lockout/Tagout (LOTO)Energy isolation procedure required before servicing any equipment
SuperintendentThe GC’s on-site construction manager; commonly called “Super”
ForemanTrade crew leader responsible for day-to-day work direction
LabourerGeneral construction worker; performs unskilled or semi-skilled tasks
JourneymanA fully certified tradesperson (electrician, plumber, carpenter, etc.)
ApprenticeA trainee working toward a journeyman certificate
Red SealA nationally recognized trades certification valid across all Canadian provinces
Site Instruction (SI)A formal written direction issued by the design team to the contractor on-site
NCR (Non-Conformance Report)Formal document issued when construction deviates from drawings or specifications
Daily Field Report (DFR)A daily log of site activities, manpower, weather, and events
Schedule of Values (SOV)A breakdown of contract value by line item; the basis for progress claims
Progress Claim / Progress DrawA payment application for work completed to date, based on the SOV

8. Common Unit Conversions

Canadian construction sites still mix Imperial (yard-pound) and Metric (SI) units. Imperial dominates in wood framing, steel, and piping.

ImperialMetric (Approximate)Site Usage
1 inch25.4 mmStandard reference
1 foot (12 inches)304.8 mmStandard reference
3/4 inch19 mm“Three-quarter”
1-1/2 inch38 mm“Inch and a half”
16 inch OC (On Center)406 mm spacingStandard stud spacing
24 inch OC610 mm spacingStud or joist spacing
4 x 8 sheet1220 x 2440 mmStandard plywood / drywall sheet size
1 PSI6.895 kPaPressure unit
1 PCF (lb/ft3)16.02 kg/m3SFRM density unit

Closing Thoughts

Canadian construction terminology can feel unfamiliar at first, but each term precisely defines a specific role, responsibility, or procedure. Treating terms as “close enough” can come back as contract disputes, safety incidents, or quality failures down the line.

In particular, contract terms (Change Order, Substantial Completion, Holdback) and safety terms (Prime Contractor, FLHA) carry direct legal liability — get them right.

If there are terms not covered here or anything you’d like clarified, drop a comment. More in-depth posts by trade are in the works.

This guide is primarily based on BC. Procedures and terminology in other provinces may differ.